Project Milestones

Project Milestones

The MLC Physical Education and Sport Precinct is a significant development that will unfold over the coming years, bringing our vision of a world-class facility to life. As we progress through each phase, we are committed to keeping our community informed every step of the way.

With the new Aquatic Centre and Junior School playground now complete, the project has moved into Phase 2. This next stage will deliver the new indoor Sports Centre, complete the underground car park and outdoor courts, and bring the full vision for the precinct to life.

The milestones below outline the key stages of construction. Timing may be refined as works progress, and we will continue to keep our community informed with regular updates throughout the project.

Construction Phases

 Phase 1

The initial phase of construction will deliver the Aquatics Centre and develop the outdoor spaces. This will also enable the current PEC to remain in use.

February 2025 - June 2026

Phase 2 

The second phase will complete the project by constructing the indoor Sports Centre, completion of the underground car park and the remaining facilities, bringing the full vision of the precinct to life with state-of-the-art amenities. The new Aquatics Centre will be operational whilst the indoor Sports Centre is being constructed. 

The details of this phase are below.

June 2026 - End 2027

Demolition

Existing Physical Education Centre (PEC) removed.

July 2026 - August 2026

Excavation

Excavation and construction of the underground car park.

August 2026 – December 2026

Structure

Sports Centre takes shape.

September 2026 – April 2027

Fitout

Internal fitout, outdoor court completion and landscaping.

February 2027 – November 2027